Aluminium Formwork System

1.  Aluminium Formwork System

Step -1 :- Detail Drawing of Mock up Shuttering . Make Sure the building architectural & structural details shall be freezed before manufacturing / fabrication of Aluminum Shuttering. It could be cumbersome  while executing the works if there is any revision in drawing

  
Step 2:-  Lets start executing the formwork. Fixing of Vertical wall reinforcement shall be done.

Step 3:-  Concrete Starters shall be done.
Step -4 :- Fixing of Wall Panels as per above shown shuttering layout. Any electrical wall conduiting can be done prior to fixing of Aluminum Shuttering.  
    
 

Step -5 :- Fixing of Slab Panels after erection of vertical wall panels

Step 6:- Concrete can be done after slab shuttering & conduiting is done.
Step 7:- Vertical walls can be removed (Deshuttering) after 24 hours of slab casting.
 


2.  Features of Aluminum Formwork
·         Sheet thickness & Panel Sizes.
·         Load bearing capacity.
·         Weight per meter square.
·         Cost per meter square.
·         Cycle time per floor.
·         Striking time for vertical & horizontal members.
·         Lead time to despatch the material.
·         Pouring system.
·         Site Assistance.
·         Design responsibility.
·         Bill of Quantity along with detailed drawing.
·         Repetition.
Sheet Thickness & Panel Sizes
·         The concrete face of panels (Al Sheet) is 4 mm thick.
·         Standard sizes of Panels are :2000x600,2000x300,1200x300,850x300.
·         Apart from above any size as required shall be manufactured and delivered.
Load Carrying Capacity
·         High load carrying capacity of 7-8 Tonnes Per square meter
Weight
·         Light weight is the  main advantage over conventional formwork technology.
·         Aluminium formwork weighs around 18-20 kg per meter square.
Cost per Meter Sq
·         The  approximate cost of aluminium formwork shall be Rs.9500.00 per meter square of shuttering area. Freight and taxes shall be  extra as applicable.

Detail costing details are already shown in earlier post. Pl refer to http://allaboutconstruction.blogspot.in/2013/10/mivan-shuttering-details.html
Cycle Time
High speed of construction can be achieved by this system that means faster completion of project.
*      7 Days per floor.
Striking time
·         Vertical (Wall) Formwork – 12 hours after concreting or when concrete strength has reached 2N/mm2.
·         Horizontal (Deck) Formwork – 36 hours after concreting or when concrete strength has reached 10N/mm2.
Pouring System
Monolithic pouring for :
  •  Slabs
  •  Walls
  •  Columns
  •  Beams
Durability
·         The panels are made out of Structural Grade Aluminum alloy.
·         Around 200 repetitions can be achieved while using Aluminium Formwork System.

Comments

dmimetals said…
It was always in my mind to read on this subject. I truly appreciate for your wonderful contribution over the same. I would like to read more from your blog site.
custom wall panel system
Preeti Mittal said…
We are Aluminum Honeycomb Sandwich Panels Manufacturers in Mumbai, India. Our Foam Sandwich Panel Construction, honeycomb composite panels utilized in a wide range of assembly procedures They will not harm substrates, unlike mechanical attaching methods; Contact us today
Charlieteo said…
Smart LED Street Lights System is architected in such way which saves energy, collects data about traffic, weather Condition, etc. Air quality monitoring sensor Canada & smart city traffic lights are installed in Canada & other countries. Contact us to more about outdoor light sensor.
Anonymous said…
The PASCHAL group is an international company specialized in formwork and formwork technology with more than 50 years of experience.

Best formwork company
Types of Formwork
Concrete Formwork System
Formwork Design
Formwork in Construction
KC Panels said…
A greatly informative blog post.

Popular posts from this blog

Construction Sequence of MEP works in Buildings

Typical Construction Sequence for Mechanical / Electrical / Plumbing Works in High Rise Building Grouping of MEP Fixes like PVC Electrical conduits in Slabs : 1. MEP 1st Fix - All Concealed Items/Pipe Sleeves in Verticals/Horizontals (Column/Slab) 2. MEP 2nd Fix - Stage 1: High Level MEP Works at False Ceiling i) Fixing supports, installation of Firefighting, Chilled Water piping, drainage pipes, water supply(hot & cold), rain water, cable ladders, G.I Conduiting, AC ducting ii) Pressure tests and insulations iii) Installation of FCUs, water heaters (Note: False Ceiling people will fix runners after the Stage 1 of MEP 2nd Fix) 3. MEP 2nd Fix - Stage 2: Clearance for False Ceiling People i) Sprinkler droppers, AC duct droppers, flexible cable for light fixtures, fire stopping and identification works etc. (Note: False Ceiling people will close ceiling tiles and MEP people will connect their diffusers in position on the ceiling tiles - too much coordination is required at

List of Top 200 Construction Companies in the world

The world's 200 largest construction companies Position Company Country 2007 Posit ion Change 1 Vinci France 1 - 2 Bouygues' Construction Divisions France 2 - 3 ACS Spain 5 2 4 Bechtel US 3 -1 5 China Rail way Group China 6 1 6 China Rail way Construction Corporation China 23 17 7 Hochtief Germany 4 -3 8 Ferrovial Spain 11 3 9 China Co mmunications Construction Group China 14 5 10 Skanska Sweden 9 -1 11 FCC Spain 25 14 12 China Stat e Construction & Engineering (CSCEC) China 13 1 13 Eiffage France 21 8 14 Kajima Co rporation Japan 8 -6 15 Fluor US 17 2 16 Strabag S E Austria 22 6 17 Taisei Cor poration Japan 10 -7 18